Installation/ General:
A. Support framing and field conditions shall be examined for compliance with installation
tolerances and other conditions affecting performance of work of this section. All OSHA rules for
erection shall be followed.
B. Deck panels shall be installed on a concrete support structure only after the concrete has attained 75% of its specified design strength.
C. Deck panels and accessories shall be installed according to the SDI Manual of Construction with Steel Deck, placement plans, and requirements of this Section.
D. Temporary shoring, if required, shall be installed before placing deck panels. Temporary shoring shall be designed to resist a minimum uniform load of 50 psf (2.4 kPa), and loading criteria indicated on Attachment C1. Shoring shall be securely in place before the floor deck erection begins. The shoring shall be designed and installed in accordance with the ACI Building Code Requirements for Reinforced Concrete and shall be left in place until the slab attains 75% of its specified design strength and a minimum of seven (7) days.
E. Deck panels shall be placed on structural supports and adjusted to final position with ends aligned, and attached securely to the supports immediately after placement in order to form a safe working platform. All deck sheets shall have adequate bearing and fastening to all supports to prevent slip off during construction. Deck ends over supports shall be installed with a minimum end bearing of 1-1/2 inches (38 mm). Deck areas subject to heavy or repeated traffic, concentrated loads, impact loads, wheel loads, etc. shall be adequately protected by planking or other approved means to avoid overloading and/or damage.
F. Butted Ends: Deck ends shall be butted over supports.
Commentary:
Lapping composite deck ends can be difficult because shear lugs (web embossment) or profile shape can prevent a tight metal to metal fit. The space between lapped sheets can make welded attachments more difficult. Gaps are acceptable up to 1" (25 mm) at butted ends.
G. Deck units and accessories shall be cut and neatly fit around scheduled openings and other
work projecting through or adjacent to the decking.
Commentary:
It is the responsibility of the designer to designate holes/openings to be decked over in compliance with applicable federal and state OSHA directives. Care should be taken to analyze spans between supports at openings when determining those holes/openings to be decked over. When a framed opening span exceeds the maximum deck span limits for construction loads, the opening must be detailed around instead of decked over. (Minimum floor construction load 50 lbs./sq. ft. (2.4 kPa), unless specific requirements dictate otherwise).
When a framed hole/opening in floor deck is shown and dimensioned on the structural design drawings, pour stop (screed) angle is required to top of slab. When specified, cell closure angle will be provided at the open ends of deck in standard 10'-0" (3 m) lengths to be field sized, cut and installed. Alternate means to dam concrete may be used in lieu of cell closure, at the discretion of the installer, if approved by the designer. When a hole/opening is not shown and dimensioned on the structural design drawings, no provisions for concrete retainage will be provided by the metal deck manufacturer/supplier. Metal floor decking holes and openings to be cut after the concrete pour shall not be field cut until concrete has reached 75% of its design strength and a minimum of seven (7) days.
H. Trades that subsequently cut unscheduled openings through the deck shall be responsible for reinforcing these openings based upon an approved engineered design.